Construction Timeline

Follow along with our construction timeline and stay up-to-date on the progress of our new upscale apartments near USC! Contact our leasing team to learn more.

Contact Us
  • 2025
    February

    Site Preparation & Grading Begins

    Work begins across the site, including grading, utilities, and general site preparation.

  • 2025
    April

    Phase 1 Foundation Work

    Foundation work starts for Phase 1 to get ready for the concrete slabs that will support the cottages.

  • 2025
    May

    Retaining Wall Construction Begins

    Retaining wall construction starts across the site. There will be over one mile of retaining wall when complete.

  • 2025
    September

    Framing Complete For Phase 1 Homes

    All homes in Phase 1 are framed.

  • 2025
    October

    Phase 2, 3, & 4 Foundation Work

    Foundation work begins for Phases 2, 3, and 4 to prepare for the cottage foundations.

  • 2025
    November

    Clubhouse Foundation Work

    Foundation work starts for the Clubhouse, and framing is completed.
    Phase 1 buildings are “dried in,” meaning the roofs, siding, windows, and doors are finished.
    Bridge construction begins in Phase 4.
    Retaining walls and all major site work, like grading and utilities, are completed.

  • 2025
    December

    Clubhouse Roof, Siding, Doors & Windows Complete

    The Clubhouse is dried in, with the roof, siding, doors, and windows completed.

  • 2026
    January

    Phase 1 Buildings Connected To Power

    The outside of the Clubhouse is finished with brick and siding.
    Permanent power is connected to all buildings in Phase 1.
    Phases 2 and 3 are framed and dried in with roofs, siding, doors, and windows.

  • 2026
    February

    Phase 1 Buildings Receive Final Inspections

    The Clubhouse receives permanent power.
    Final inspections are done for all Phase 1 buildings.
    Bridge construction in Phase 4 is completed.
    All Phase 4 buildings are framed and dried in with roofs, siding, doors, and windows.

  • 2026
    March

    Clubhouse Receives Final Inspections

    Final inspections are completed for the Clubhouse.

  • 2026
    April

    Phase 2 & 3 Buildings Connected To Power

    Permanent power is connected to all buildings in Phases 2 and 3.

  • 2026
    May

    Phase 2 Buildings Receive Final Inspections

    Final inspections are completed for Phase 2.
    Permanent power is connected to all buildings in Phase 4.

  • 2026
    June

    Phase 3 & 4 Buildings Receive Final Inspections

    Final inspections are completed for Phases 3 and 4.

  • 2026
    August

    Move-In Day

    Residents move in at The Narrative at Columbia.